本文二维码信息
二维码(扫一下试试看!)
综合法二氧化氯生产系统废水除铬实例
Example of Chromium Removal from Wastewater in a Synthetic Chlorine Dioxide Production System
收稿日期:2023-10-16  
DOI:10.11980/j.issn.0254-508X.2024.04.023
关键词:  二氧化氯  二氧化硫还原法  含铬废水  六价铬去除率
Key Words:chlorine dioxide  sulfur dioxide reduction method  chromium-containing wastewater  removal rate of hexavalent chromium
基金项目:
作者单位邮编
谢勤 海南金海浆纸业有限公司海南儋州578101 578101
李丽萍 海南金海浆纸业有限公司海南儋州578101 578101
崔召锋 海南金海浆纸业有限公司海南儋州578101 578101
潘世道 海南金海浆纸业有限公司海南儋州578101 578101
摘要点击次数: 950
全文下载次数: 3
摘要:以某浆纸厂含铬废水处理工程实例为研究对象,针对综合利用自产化学药品和现有设备开发的间歇性六价铬(Cr6+)综合处理系统,探讨了二氧化氯车间Cr6+废水产生原因及性质,根据不同的反应池pH值、反应温度、反应时间和硫磺投加量对废水中Cr6+还原效果的影响,确定了二氧化硫还原法去除Cr6+的最佳反应条件,并结合实际生产数据,展示了Cr6+还原效果。结果表明,有效去除高浓度含铬废水中Cr6+的条件为:pH值=2~4、反应温度控制在40~60 ℃、硫磺投加量为理论反应所需投加量的1.4~1.6倍、反应时间40 min。3次二氧化氯车间停修废水出水中Cr6+含量均低于0.005 mg/L,总铬含量均低于0.06 mg/L,符合《污水综合排放标准》(GB 8978—1996)中的要求,证实了间歇性Cr6+综合处理系统处理的有效性。
Abstract:In this paper, a new engineering example for the treatment of chromium-containing waste water in pulp and paper mill as the research object, for the intermittent hexavalent chromium(Cr6+) comprehensive treatment system that developed by the comprehensive use of self-produced chemicals and existing equipment, the reasons for the generation of Cr6+ wastewater in the chlorine dioxide workshop and the properties of the wastewater were analysized. Based on the effects of different pH value of reaction pool, reaction temperature, reaction time, and sulfur dosage on the reduction effect of Cr6+ in wastewater, the optimum reaction conditions of the sulfur dioxide reduction process for removing Cr6+ were determined, and the reduction effect of Cr6+ was demonstrated in combination with the actual production data. The results showed that the optimum conditions for the effective removal of Cr6+ from high concentration chromium-containing wastewater were that pH value of 2~4, reaction temperature of 40~60 ℃, sulfur dosage of 1.4~1.6 times of the theoretical dosage required for the reaction, and reaction time of 40 min. The content of Cr6+ in the effluent of wastewater from the three shutdowns of chlorine dioxide workshop was lower than 0.005 mg/L, and the content of total chromium was lower than 0.06 mg/L, which were in line with the requirements in the GB 8978—1996, confirming the effectiveness of the treatment of the intermittent Cr6+ comprehensive treatment system.
查看全文  HTML  查看/发表评论  下载PDF阅读器